The project improvements will include:
- Enhanced crossing with a refuge island on SE Century Boulevard north of SE Damask Street
- School crossing on SE 67th Avenue at SE Genrosa Street
This project is being primarily funded through the Oregon Department of Transportation Safe Routes to School Construction Grant.
Activity
Engineering for the SE 67th Avenue/Genrosa Street crossing portion of the project is completed and construction is scheduled to be completed by early winter 2022. The Century Boulevard crossing is in the pre-design phase.
Project Timeline
67th Avenue/Genrosa Street Crossing
- Design: fall 2021 (completed)
- Construction: fall 2021 – winter 2022
Century Boulevard Crossing
- Design: spring 2021 – spring 2022
- Construction: spring 2022 – fall 2022